Silver Star Bicycle Company will be manufacturing both men’s and women’s models of its Easy-Pedal bicycles during the next two months. Management wants to develop a production schedule indicating how many bicycles of each model should be produced in each month. Current demand forecasts call for 150 men’s and 125 women’s models to be shipped during the first month and 200 men’s and 150 women’s models to be shipped during the second month. Additional data are shown:

Model

Production Costs

Current Inventory

Men’s

$120

20

Women’s

90

30

The company charges monthly inventory at the rate of 2% of the production cost based on the inventory levels at the end of the month. The company would like to have at least 25 units of each model in inventory at the end of the two months.

Formulate this problem as a linear programming model so that a production schedule can be established in order to minimize production and inventory costs and satisfies the labor-smoothing, demand, and inventory requirements.

Adirondack Paper Mills, Inc., operates paper plants in Augusta, Maine, and Tupper Lake, New York. Warehouse facilities are located in Albany, New York, and Portsmouth, New Hampshire. Distributors are located in Boston, New York, and Philadelphia. The plant capacities and distributor demands for the next month are as follows:

Plant

Capacity (units)

Augusta

300

Tupper Lake

100

Distributor

Capacity (units)

Boston

150

New York

100

Philadelphia

150

The unit transportation costs (in $) for shipments from the two plants to the two warehouses and from the two warehouses to the three distributors are as follows:

Plant

Warehouse

Albany

Portsmouth

Augusta

7

5

Tupper Lake

3

4

Warehouse

Distributor

Boston

New York

Philadelphia

Albany

8

5

7

Portsmouth

5

6

10

Draw the network representation of the Adirondack Paper Mills problem.

Formulate the Adirondack Paper Mills problem as a linear programming problem. You do not need to solve the model.

Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) complete date is desired. The condominium manager identified the following renovation activities and their estimated times:

Activity

Immediate Predecessor

Time

A

3

B

1

C

2

D

A, B, C

4

E

C, D

5

F

A

3

G

D, F

6

H

E

4

Draw a project network.

What are the critical activities?

Will the project be completed by September 1?

Doug Casey is in charge of planning and coordinating next spring’s sales management training program for his company. Doug listed the following activity information for this project:

Activity

Immediate Predecessor

Time (weeks)

Optimistic

Most Probable

Pessimistic

A

1.5

2.0

2.5

B

A

2.0

2.5

6.0

C

1.0

2.0

3.0

D

C

1.5

2.0

2.5

E

B, D

0.5

1.0

1.5

F

E

1.0

2.0

3.0

G

B, D

3.0

3.5

7.0

H

G

3.0

4.0

5.0

I

F, H

1.5

2.0

2.5

Draw a project network.

What are the critical activities and what is the expected project completion time?

If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project?

Due Date: Jul 30, 11:59pm

Note: Homework solution must be submitted electronically to Homework 4 folder in Assignment on D2L.

It is your choice to submit all of your work or just the final answer only. If you only submit the final answer and the answer is wrong, you will lose all the points assigned to that question. If you also show the steps how you get that answer, you still can earn partial credit as long as the steps are not completely wrong.

The post MGT 3410 Homework 4 Summer 2023 Chapter 8&9 and 11 Silver Star appeared first on essayfab.

MGT 3410 Homework 4 Summer 2023 Chapter 8&9 and 11 Silver Star
Scroll to top